Sunday, December 7, 2014

Official site development submittal - project update #005


This week was very eventful. First of all we had demolition permits issued by City of Austin. That took a few months, but we finally got the result.

Second after completeness check was passed we had a formal official site development submittal on Thursday, Dec 4. That started the clock with the city – we are on schedule to receive our permits by May 2015.

Third we paid the first earnest money deposit to extend the closing by 30 days. We still have 5 more extensions, which should give us sufficient time to get development and building permits.

We were also introduced to Victor Demarco from American Geothermal (http://amgeosystems.com/) and we want to go ahead using geothermal HVAC system, as it is the most efficient, green and reliable system that is currently available:




The building design  has been updated to have more windows and optimized unit layout.